Milestones

Milestones

Milestones

The company was established on December 5th.

 

  • The signing of the Power Purchase Agreement (PPA) for the IPP Jawa-1 project took place on January 31st.
  • The Power Purchase Agreement (PPA) takes effect starting from September 15th.
  • The signing of the Ship Building Contract between JSP and SHI took place on October 23rd.
  • The signing of the Onshore & Offshore Long-Term Service Agreement (LTSA) between JSP and GE took place on December 21st.
  • The acquisition of zoning and onshore location permits took place on January 19th.
  • Signed the PPA amendment and contract of the IPP Jawa-1 Project on March 26th.
  • Appointment of construction and licensing consultant, as well as initiation of permitting, on May 15th.
  • Obtained AMDAL permit on June 5th.
  • Issuance of Limited Notice to Proceed (LNTP) to EPC on August 15th.
  • Implementation of Environmental and Social Impact Assessment (ESIA) and acquisition of Tower Footing and HGB in September.
  • Amendment No. 1 to the Onshore & Offshore Long-Term Service Agreement (LTSA) between JSP and GE on October 12th.
  • Amendment to the Power Plant Construction Contract between JSP and EPC on October 12th.
  • EBL Facility Agreement between JSP, PT Pertamina Power Indonesia, and Bank MUFG on November 26th.
  • Implementation of EPC NTP and Financial Close for the IPP Jawa-1 project on December 5th.
  • The groundbreaking ceremony symbolizing the commencement of the Jawa-1 Combined-Cycle Power Plant project.
  • The construction of temporary facilities in Cilamaya on March 31st.
  • The steel cutting for the Floating Storage Regasification Unit (FSRU) Jawa Satu took place on April 26th in South Korea.
  • The completion of the project for installing 6,000 foundation piles with an average height of 30 meters on June 4th.
  • The fabrication of the gas offloading platform and mooring jetty for the FSRU took place on February 26th.
  • The installation of the Heat Recovery Steam Generator (HRSG) within the power plant took place on March 23rd.
  • JSP participated in the naming ceremony of the FSRU.
  • A total of 118 towers and 52 km of 500kV transmission lines successfully facilitated the distribution of electrical power on August 19th.
  • The distribution of electrical power from the Cilamaya U1 500kV transformer took place on August 19th.
  • The distribution of electrical power from the Cilamaya U2 500kV transformer took place on September 23rd.
  • The production of demineralized water took place on November 5th.
  • The first gas was transported from the FSRU through a 21 km gas pipeline on December 27th.
  • The implementation of the First Firing for Unit 1 took place on February 23rd.
  • The first implementation of Trash Blow took place on February 24th.
  • The re-firing of Unit 1 took place on November 28th.
  • The implementation of the First Synchronization for Unit 1 took place on December 6th.
  • The implementation of the First Firing for Unit 2 took place on December 20th.

PT Jawa Satu Power (JSP) or Jawa-1 Project is joint venture a joint venture between PT Pertamina Power Indonesia (“PPI”), Garuda Power Holdings B.V., and Sojitz Global Investment B.V. On December 5, 2016, the Company was founded as Special Purpose Company (SPC) to run, control, and manage assets and business activities of gas-fired power plants with the largest CCGT technology in Southeast Asia.

Contact Us

en_USEnglish